New end date for Mill Dam bridge project in Centerport

Community Watchdog readers from Huntington, especially those in the Centerport area, probably noticed that the town has missed its April 1 date for finishing work on the Mill Dam bridge and causeway area.

Area residents should be getting a letter any day now, explaining the delay.

The project turned out to be bigger than planned and then community input added more time that nobody counted on.

Town of Huntington spokeswoman Fran Evans said the project’s original $1.6 million budget grew to $2.3 million. Part of the $700,000 in additional costs includes expanded work on the causeway because more of it was falling apart than anyone realized and a special guide rail.

Some residents complained about the steel guide rail that was planned for the site. They wanted a wood rail, like the one that had been there previously. But wood guide rails splinter and have been banned. So, trying to accommodate the residents, the town searched for and found a steel-backed timber rail that cost more, but satisfied the residents who thought it was important enough to delay the project for it. It’s been ordered and should be delivered within four weeks, according to a letter being sent to residents by Supervisor Frank Petrone and the town board members.

“We are aware of the inconvenience that this has caused the community and apologize for the delays,” the letter states. “We are confident the final product will meet with your approval and that the addition of sidewalks, lighting and new railings will very much add to the charm and character of the community.”

Between the guide rail issue, the expanded work on the causeway and other details needed to complete the project, the new completion date is set for the end of June, Evans said.

TrackBack

TrackBack URL for this entry:
http://blogs.trb.com/cgi-bin/mt/mt-t.cgi/71563

Post a comment


Please enter the security code you see here

gwen_young_right_rail.jpg
Put your community watchdog to work
Getting the runaround from Town Hall? Got a problem the village won’t fix? Send Gwen Young your questions, she'll get you the answers.

Categories

Video